Portfolio - Commercial

Marcus Garvey

30 week fit-out of 20,000sq.ft commercial space forming offices, meeting rooms, interactive space and associated toilet and kitchen facilities in North London.

  • £2,500,000 / 30 week construction programme
  • Complete strip-out of ground and 1st floors
  • Removal of metal access stairs and hollow rib deck / concrete infill
  • New M&E services including CCTV, alarm etc. and plant room works
  • Installation of new structural concrete cantilever stairs constructed on-site
  • Raised access and computer flooring installed throughout
  • Installation of suspended StoSilent panel seamless acoustic ceiling system
  • Formation of new glazed and stud partitions alternative room layouts
  • New Maple doors, frames and skirting along with new Dorma sliding doors
  • Installation of Boon Edam revolving entrance door and new reception area
  • Complete decoration throughout
  • Refurbishment and alteration works to lift
  • Construction of disabled access ramp including stainless steel handrails
  • New office space, kitchen areas and toilets

Project Details

  • Client: Marcus Garvey, Commercial Client
  • Contract Value: £2,500,000
  • Project Type: Fit-out
  • Contract Duration: 30 weeks
  • Form of Contract: JCT Standard Contract
  • Lead Consultant: Frankham / Playle & Partners
T&B Interiors