Givenchy

Working alongside GAD Design and in close coordination with Bicester Village’s in-house landlord team Value Retail we transformed the empty unit into Givenchy’s new high-end retail store; thier first standlaone store in the UK.

  • 5 week construction programme
  • Complete fit-out of Givenchy’s high-end retail unit
  • Construction of partition from mezzanine to front of house
  • Installation and construction of bespoke Italian shelving and display units
  • Extensive M&E services including AV, CCTV and security tagging system
  • Installation of bespoke parquet and timber flooring
  • Full decoration throughout
  • Installation of track lighting and showcase unit lighting
  • Formation of fitting rooms and in-store disabled toilet
  • New Givenchy motifs and livery
  • Creation of ‘back of house’ store and office on mezzanine floor
  • Coordination with Bicester Village’s landlord Value Retail

Project Details

  • Client: Givenchy
  • Contract Value: Confidential
  • Project Type: Fit-out
  • Contract Duration: 5 weeks
  • Form of Contract: JCT Minor Works
  • Lead Consultant: GAD Design